PROJECT # 3881 Unit 1 - Line E
Hollyhills Drain Unit 8B Phase II




Scope of Work:

4500 L.F. of 66" and 84" storm drain installation under the paved roads of West Hollywood. Average depth of 26 ft. deep under extreme conditions with excessive ground water and poor soils. 4052 L.F. of micro tunneling (bored and jacked) of both 66" and 84" reinforced concrete pipe. Installed several junctions structures and manholes. Relocated existing sewer mains and also existing water mains. Replacement of curb and gutter and asphalt resurfacing.